Hydrocracker/ Hydrotreater modernization and construction project for NIS Petroleum Industry of Serbia in Pancevo


1
2
    
3
    
4
    
5
    
6
    
7
    
8
    
9
    
10
       
11
       

  • period : December 2010 - March 2012 
  • weight and dimensions of heavier pieces: 485 tonnes, 24x6,4x6,2 m and 530 tonnes, 34x4,5x5,9 m 
  • transportation, construction works, lifting and installation of equipment included:
    • strengthening of nearest berth to the refinery on Danube to ensure safe off-loading of heavy equipment;
    • strengthening of  the bridges on the route from the berth to the refinery, using bridge-over-bridge system;  
    • transportation of the equipment on the route port Marghera, Italy – Rotterdam – delivery by 2 self propelled barges by Rein – Danube rivers;
    • off-loading, inland transportation, super-lifts and installation of heavy reactors and separator at site;
    • lifting and installation on the  foundation of more that 50 pieces of heavy equipment at the refinery.
  • main equipment used for off-loading and on-site delivery and installation of reactors:
    • multipurpose heavy lift (geared) vessel;
    • 2 self-propelled barges;
    • LR1750 and  CC2400-1 crawler cranes with the capacity of 750 tonnes and 450 tonnes respectively;
    • 4 x 12 axle lines Kamag SPMT's.