• strengthening of nearest berth to the refinery on Danube to ensure safe off-loading of heavy equipment;
• strengthening of the bridges on the route from the berth to the refinery, using bridge-over-bridge system;
• transportation of the equipment on the route port Marghera, Italy – Rotterdam – delivery by 2 self propelled barges by Rein – Danube rivers;
• off-loading, inland transportation, super-lifts and installation of heavy reactors and separator at site;
• lifting and installation on the foundation of more that 50 pieces of heavy equipment at the refinery.
• multipurpose heavy lift (geared) vessel;
• 2 self-propelled barges;
• LR1750 and CC2400-1 crawler cranes with the capacity of 750 tonnes and 450 tonnes respectively;
• 4 x 12 axle lines Kamag SPMT's.